Invitation for Bids (IFB)
08, June 2021
Mongolia
MON-14
Heating System Improvement Project of 10 Mongolian Province Centers
LOT 3
/Khentii/Sukhbaatar/Govisumber/
Brief Description of Works
[Total budget]
Bidding Lot 3 total budget - US$ 33,642,000.
[Nationality of Entities]
The single entity or all the entities consisting of a Joint Venture who is (are) the Korean nationality holder(s) at the time of bidding shall be eligible for the bidding as per the requirements of the Loan Agreement.
[Pending Litigation]
All pending litigations of either a single entity or each member of Joint Venture shall be treated as resolved against him, and so shall any entity in total exceeding more than fifty (50) percent of his net worth shall not be eligible for the bidding.
[Historical Financial Performance]
As a minimum, the net worth of an entity calculated as the difference between total assets and total liabilities shall be positive for the last three (3) years.
[Average Annual Construction Turnover]
The Average Annual Construction Turnover of an entity or entities combined shall be, at least, thirty million US dollars (US$ 30,000,000) calculated as total certified payments received for contracts in progress or completed, within the last three (3) year. And, when a Joint Venture is made for the bidding, it shall be eligible for the bidding only if each member shall have, at least, twenty-five (25) percent of this amount, and, additionally, one member of whom shall have forty (40) percent of this amount as well.
[Financial Resources: Cash Flow Generation Capability]
The single entity Bidder shall demonstrate access to, or availability of financial resources such as the liquid assets of cash flow or something equivalent, unencumbered real assets, lines of credit, and other financial means, other than any contractual advance payments, the amount of thirty percent (30%) of the Bidding Lot 3 total budget.
For the Bidder of a Joint Venture, all members jointly shall meet the above amount of cash flow generation capability, and each member shall be able to demonstrate the capability of forty percent (40%) of this amount individually, and additionally, at least, one member shall have the capability of sixty percent (60%) of this amount for the qualification.
[Specific Construction Experience]
Only either the single entity or all the entities combined having the track records of three (3) or more Energy Related Plant projects such as the power plants, oil & gas plants, and the heating plants with the distribution networks for district heat supply (except for waste incinerator only plants, water and waste water treatment plants) during the previous ten (10) years from the bid open date, his own portion of which the contract amount individually shall be equal to or exceed ten million US dollars (US$ 10,000,000) and, at least, one of which shall be equal to or exceed thirty million US dollars (US$ 30,000,000) is (are) eligible for the bidding.
[Construction Experience in Key Activities]
Either a single entity or all the entities of a Joint Venture combined shall have the following construction experience to be eligible for the bidding through the demonstration of the following construction experiences.
Each of the following requirements shall be met as the key activity in a single project.
Account Name: Ministry of Finance (100900011609)
Account No.: 106000079576
Beneficiary’s Bank: State Bank of Mongolia, Ulaanbaatar, Mongolia
SWIFT code: STBMMNUB
Correspondent bank: KOOKMIN BANK
SWIFT code: CZNBKRSE
Account No.: 7968USD019
The document will be provided to registered representative of the Bidders by hard copies and PDF files from the day of Bid issued, and additionally, the workable files in the Excel Sheets.
If you are unable to purchase a Bidding Document in Mongolia, you can send a representative who can purchase in Mongolia.
This Invitation shall take effect until at 17:30 local time on 22, July 2021, after publication in the official website or in a newspaper of general nationwide.
Address: “Heating system Improvement Project of 10 Mongolian Province Centers” Project Implementation Unit’s office, 7th floor, Polaris tower, Chinggis avenue, 2nd khoroo, Khan-Uul district, Ulaanbaatar, Mongolia, 17040
Representative: Oyun.D, Engineer of “Heating system Improvement Project of 10 Mongolian Province Centers” Project Implementation Unit.
E-mail: oyun@energy.gov.mn
Telephone: +976-70001189